Project Name: CIP #2009-03 - 25th Avenue NE Water Main Extension
Project Boundaries: Project starts at NE 190th St. and 18th Ave NE. It goes South to Perkins Pl NE on south to 25th Ave NE to NE 178th St. There is a short extension on NE Perkins Way from 18th Ave NE east to the school.
Purpose: This project will be a Transmission Water Main to keep water quality excellent in the area.
Time Frame: The start date was April 26th for 75 working days.
Consultant: BHC Consultants
If you need further information about this, or any other project in the District, please contact Denny Clouse, Operations Manager at 206.362.8100.